Bayliss Boatworks new construction update - Bayliss 68' Overtime
by Bayliss Boatworks 2 May 2022 05:45 PDT
Bayliss 68' Overtime © Bayliss Boatworks
Progress continues in the cockpit on Overtime!
The teak border, cockpit deck, and coverboards were all installed in April. Our paint crew has also been hard at work with the priming of the mezzanine now complete.
In the lower accommodations, the master bunk and cabinetry have been installed. Next month on Overtime, our crews will be finishing up the mezzanine buildout.