Benefits of NZ Govt's America's Cup plan evaporating
by Todd Niall, Radio NZ 30 Jan 2018 02:27 PST
30 January 2018
Wynyard Point looking towards Auckland City and Hobson Wharf © Richard Gladwell
Auckland Council on Tuesday starts the planning process for its preferred village option, with the clock ticking on cabinet minister David Parker's determined bid to find an alternative.
Mr Parker wears two hats: as the Minister for Economic Development and Minister for the Environment, with the latter being the hat that seems to fit best in this pressured scenario.
He is mostly unhappy that the council proposal involves extending Halsey Street wharf by 75m, Hobson Wharf by 74m, and a narrow extension on Wynyard Wharf.
Mr Parker opposes the encroachment of piled-wharf construction over the open water of the inner port area to accommodate the sailing regatta planned for the summer of 2020/2021.
Over the summer however, the wharf extensions in government's own plan have grown: on Halsey Street Wharf from 15 to 25 metres, with Hobson Wharf as large as in the council option, and with some bases on Wynyard Point.
Mr Parker continues to argue that the Wynyard Point plan, which puts more bases on existing land, would be cheaper but updated costings have not been released.
Wynyard Point was originally costed at $16 million less that the council option's $128 million, and that was before government officials found that their Halsey Street wharf extension would have to grow by two-thirds.
Auckland Council's outline of how it's village layout could be used post-America's Cup.Auckland Council's outline of how it's village layout could be used post-America's Cup. Photo: Supplied
So, going into what might be the final week of the behind-the-scenes wrangling, here are the key issues :
The council says its mainly new-build option poses few risks in the tight timeline to having the bases planning-consented and ready by late next year.
The expanded government option still accommodates only seven teams, not eight, and the larger, two-boat challengers would find themselves on the semi-industrial Wynyard Point furthest from the inner-harbour "arena".
The economic benefit to the country increases as the number of teams increases, according to MBIE research.
The government option requires the negotiated early departure of bulk storage tanks owned by Stolthaven, which mayor Phil Goff says is asking $6.1 million as a lease-break fee.
David Parker says the costs of cleaning up the sites would have to be met by the council in any event, but the council would lose the ability to recoup costs because the planned sale of nearby sites would stall.
Auckland Council has been committed to a coordinated development of a headland park on Wynyard Point from 2022, funded by neighbouring commercial property, and a marine industry sector. It is uncertain whether the government offers the same.
The council, through its development agency Panuku, says both the time needed and the potential cost of the toxic clean-up are risks the project can't afford. David Parker says the government option would be cheaper and quicker to obtain planning consents for - a point contested by Auckland officials. Auckland's mayor says whatever the government ends up proposing, it needs to meet cost and time-to-build criteria, and also be acceptable to cup defender Team New Zealand. (The team's challenger-partner Luna Rossa is unlikely to want to be sidelined into a semi-industrial site)
The economic benefit from the America's Cup - the main ground for public investment - is put at up to $1 billion, with the number of competing teams, and the number of Superyacht visits and maintenance: the chosen option needs to deliver that.
RNZ understands that the government "team" led by top commercial governor Michael Stiassny, is hoping to finalise its work by midweek, but Mr Parker told RNZ it might take longer.
For the full story click_here